US Army Corps of Engineers  Section §206 

Royal River Restoration Project

The USACE DRAFT Detailed Project Plan and Habitat Assessment has been released.  

Email your comments to the Yarmouth Town Council and USACE project team by Nov 15th: RoyalRiverYarmouthMe@usace.army.mil Your comments will provide feedback to the town council.

Town of Yarmouth Public Meetings and Dates

Oct 11/2024:  Public comment period begins, email to: royalriveryarmouth@usace.army.mil (by Nov 15)

Oct 10/2024:  USACE DPP/EA River Abutters Meeting

Oct 9/2024: USACE Hosted: Royal River (Section 206 Study) Public Meeting

Oct 9/2024: USACE DRAFT Integrated Detailed Project Plan and Environmental Assessment 

Aug 2024: USACE Hydrology & Hydraulics Study Public Meeting Recording

Aug 2024: USACE Hydrology & Hydraulics Study Public Presentation Slides

Jul 2024: Yarmouth Gooch Island Neighborhood Meeting PowerPoint

May 2024: USACE Tentatively Selected Plan Fact Sheet

May 2024: USACE Benefits Per Alternative, Tentatively Selected Plan, Cost Estimate Presentation Slides

Feb 2024: USACE Sediment Composition and Probing Presentation Slides

Feb 2024: USACE Sediment Composition and Probing Presentation Slides

May 2024: USACE Benefits Per Alternative, Tentatively Selected Plan, Cost Estimate Presentation Slides

Mar 2023: USACE Hydrology & Hydraulics Preliminary Data Public Meeting Recording


Town of Yarmouth Royal River Restoration Information 

Frequently Asked Questions answered by the Town of Yarmouth.

USACE Bi-Weekly Project Meetings, Minutes  and Timeline

12/16/24


Date: December 16, 2024, 3:15 pm  Present: Janet Cote, Project Manager (remote); Karin Orenstein (remote)


Janet reported that the Project Delivery Team (PDT) is in a holding pattern as they are almost out of project funds.  At this point, the Agency Technical Review is completed, while the legal and policy review and public comments remain to be addressed.  Once USACE receives the requested funds, they will proceed to complete these tasks and finalize the report.  Karin advised that the $81k request was on the Town Council’s December 19th agenda.  Janet confirmed that the reasons that the project costs were higher than estimated is that the original estimate did not include (1) Middle Falls, (2) community concerns about Gooch Island or (3) the level of public engagement.  All of these have made for a better project, but have required more of USACE’s time and effort than originally anticipated.

Janet and Karin noted the ongoing email communication between Bill Mehr (PDT-Real Estate) and Maine DEP about riparian rights and permitting.

Karin asked whether the scope of the USACE project could include impacts on infrastructure (specifically, the dry hydrant in North Yarmouth noted in the draft report) and stakeholders (specifically, harbor businesses seeking risk mitigation insurance).  Janet does not believe the dry hydrant will be impacted based on information available to the PDT while working on the draft report.  However, it’s possible that during the design & implementation phase, USACE would learn more about the hydrant and change their position.  Janet will find out whether impacts on infrastructure, such as the efficacy of a dry hydrant, could be included in the scope of USACE’s project.  Similarly, while USACE does not believe there is a risk of contamination or increased dredging, she will look into whether the project scope could include insuring against that risk.  Janet will also ask the dredging side of USACE for their views on whether the (much larger) federal navigational channel dredge would be impacted and what, if anything, they are doing to address that risk.

The meeting ended at 3:40 p.m.

END

12/02/24


Date: December 2, 2024. 3:15pm Present: Janet Cote, Project Manager (remote)

Karin Orenstein (remote); Scott LaFlamme (remote)


- Janet Cote (USACE Project Manager) reported that the Project Delivery Team (PDT) is

continuing to address questions and comments from the Agency Technical Review (ATR). In

addition to responding to ATR items, the team is also reviewing questions from the USACE’s North Atlantic Division (NAD).


Donnie Faughnan (USACE Wildlife Biologist) is compiling all questions and comments

submitted during the NEPA-required 30-day concurrent review process. All public comments will be incorporated into the USACE’s final feasibility report.


Scott LaFlamme is working with representatives from the Maine Department of Environmental Protection (DEP) to address questions regarding the need for in-water temporary access easements at the three project sites.


- Janet clarified that the U.S. Fish and Wildlife Service did submit a letter that provided the

Resource Agency’s official opinion of the project as part of the 30-day concurrent review

process. They agency completed a site visit in June 2024.


- In response to earlier questions about a possible locally preferred plan (LPP) that would study a nature-like fishway, Janet provided the Project Study Team with a cost estimate for

evaluating that alternative. The estimated cost for this work is $480,000. She also noted that if the Town chooses to pursue a nature-like fishway, ongoing maintenance of the East Elm Street dam will be necessary to maintain the required water height and flow along the fishway. 


The meeting was adjourned at 3:30pm.

END

11/04/24

USACE Section 206 Study Bi-Weekly Project Update

Date: November 4, 2024. 3:15pm

Present: Janet Cote, Project Manager (remote), Karin Orenstein (remote), Scott LaFlamme (remote)


Janet Cote, USACE Project Manager, reported that the Project Delivery Team (PDT) continues to receive questions and comments from the public. All electronic and written correspondence has been forwarded to the Town, where it is being compiled for review by the Town Council during their deliberations. In addition to gathering public input, Janet noted that the PDT is actively addressing a number of internal questions through the USACE’s Agency Technical Review (ATR) process.


While the PDT is working to respond to public inquiries as quickly as possible, responses to ATR questions are due by the end of this week, making internal queries the current priority for USACE. All questions submitted by the public will be addressed as soon as reasonably possible, but responses are not expected to be completed within the 30-day public comment period.


Royal River Task Force members are continuing to develop questions related to the draft Detailed Project Report/Environmental Assessment (DPR/EA). Karin will send priority questions to Janet from the RRTF in the hopes they can be responded to in time to be included in their deliverable to the Town Council.


The Town Council will hold a Special Meeting on Thursday, November 7th, at the Log Cabin, prior to its regular Workshop meeting. During this meeting, a public hearing will be conducted to gather comments related to the Section 206 study of the Royal River. A second public hearing is scheduled for November 21st at 7:00 pm, also at the Log Cabin. No Town Council action is expected at either meeting.


Janet will send Scott an estimate and breakdown for upcoming fund requests.


Karin asked why the draft report quoted FWS’s letter stating that chipping at two locations in the back channel at Middle Falls would be sufficient, but then did not explain why that option was screened in favor of the more expensive water diversion option. Janet will try to get an answer but noted that FWS has not submitted a report from its site visit.


The meeting was adjourned at 3:30pm. 

Please remember that the deadline for public comment on the draft report is November 15th.  Comments and questions can be emailed to USACE at: RoyalRiverYarmouthME@usace.army.mil

END

10/21/24

USACE Section 206 Study Bi-Weekly Project Update

Date: October 21, 2024. Present: Janet Cote, Project Manager (remote), Christopher Tilley, USACE Cost Engineer (remote), Karin Orenstein (remote), Scott LaFlamme (remote), Michelle Cromarty (remote), Debbie Landry, Royal River Task Force Member (remote), Mike Brandimarte, Royal River Task Force Member (remote)

- Janet Cote (USACE Project Manager) reported that the Project Delivery Team (PDT) has received numerous comments from the public during the 30-day concurrent review process. All electronic correspondence has been shared with the Town, where it is being collected for future Town Council review. Janet also shared that in addition to soliciting public comments, the PDT is fielding questions and comments from a variety of other USACE divisions and State and Federal agencies.

- Chris Tilley (USACE Cost Engineer) was available to answer questions related to the Tentatively Selected Plan’s (TSP) project budget. He and Janet responded to several questions related to the proposed adaptive management plan and five-year monitoring program. The $50,000 budget ($10,000 per year for five years) for monitoring will allow the USACE to analyze whether the improvements are hitting the habitat unit benchmarks that have been developed along the study area. The cost of adaptive management measures outside of what has been included in the draft report will be split between the USACE and the Town of Yarmouth (65% USACE, 35% Town).

- Members of the Royal River Task Force raised several questions about the metrics used to project the habitat unit total in the draft report. They would like to know more about similar case studies or the best available data sets that helped to inform those totals. They also hope to learn more about how the USACE plans to track the success of the project, should the Town endorse the TSP. Janet will work with Donnie Faughnan (USACE Biologist) to answer those questions prior to the next project update meeting.

- The Yarmouth Town Council formally established the Joint Committee on Royal River Recreation and Ecology during their most recent voting meeting. The Committee, which will be comprised of two Yarmouth Town Council members, two North Yarmouth Selectboard members and a resident from each community, is also being created in North Yarmouth. Together, the two communities are committed to addressing shared challenges and opportunities along the Royal River.

- The Royal River Task Force will be hosting a public open house event on Monday, October 28th at 6:00pm in the Log Cabin. Here, the Task Force will welcome questions and comments related to the draft Detailed Project Report/Environmental Assessment. The public’s feedback will be important to guiding their work and future Town Council decisions. The meeting was adjourned at 4:10pm.

END

10-09-24

USACE Section 206 presented "The DRAFT Integrated Detailed Project Plan and Environmental Assessment"  for public comment and questions.

This meeting was held in person at 6PM in the Patriot Insurance building on Rte. 1 and was also available virtually. The DRAFT DPP/EA report was released on October 11. 


Following the meeting, a 30 public comment period begins on October 10 to November 10th.

Send comments or questions to USACE and Town of Yarmouth using this link

Meeting ended at 8 PM.

9-23-24

USACE Section 206 Study Bi-Weekly Project Update

Date: September 23, 2024. 3:15pm Present: Janet Cote, Project Manager (remote), Karin Orenstein (remote), Scott LaFlamme (remote)


The meeting was adjourned at 3:40pm. 

END

9-11-24

USACE Section 206 Study Bi-Weekly Project Update

Date: September 11, 2024. 3:15pm. Present: Janet Cote, Project Manager (remote), Karin Orenstein (remote), Scott LaFlamme (remote)


- Members of the Study Coordination Team met for the first time in several weeks. Janet,

along with members of the Project Delivery Team (PDT), has been working hard to finalize the draft Detailed Project Report/Environmental Assessment (DPR/EA). Since the Study Coordination Team’s last meeting, the draft DPR/EA has been completed and it is now being reviewed by USACE’s Office of Counsel for legal compliance. Once cleared by legal, the draft report can be shared with the public, at which point the Town and USACE can finalize details for a public meeting. This meeting will signify the beginning of the Corps’ NEPA-required 30-day public review process. Janet expects that the draft report will be available for public review in early October, coinciding with a public meeting to kick off the 30-day period. When the draft report is available to the public, USACE will provide two hard copies for public review at public facilities.


- Once a date is set for the public meeting, Scott will coordinate with local venues that can accommodate a larger than normal crowd. As logistics are finalized (as early as next week), the Town will be mailing an informational postcard to every Yarmouth resident with meeting details. The meeting will be available virtually as well, meaning that residents can participate in person or from home.


- In addition to hosting a community-wide public meeting, members of the PDT will also host a smaller public meeting with Royal River abutters to discuss potential real estate impacts. All direct abutters, from Sparhawk Mill to Baston Park, will be invited to attend. Logistics for this meeting are also being finalized. Once a date and location are determined, USACE will reach out to property owners directly with additional information.


- As the Town continues to explore opportunities to better inform the community on this initiative, members of the Study Coordination Team shared the following:

o Karin volunteered to write an executive summary for the draft DPR/EA from the Town, in hopes of simplifying an incredibly technical report.

o The Town successfully released three informational videos on its social media channels and website to educate the public on the study’s history and potential next steps. A fourth video will be released soon to share information on the recently completed H&H model of the Royal River.

o Karin manned an information table about the river restoration project at the Farmer’s Market on six Thursdays over the summer, speaking with over 100 residents of Yarmouth and nearby towns.

o The Town Council recently appointed a Royal River Task Force to assist in reviewing the draft DPR/EA and sharing thoughts with the Town Council on potential next steps.


The meeting was adjourned at 3:45pm.

END

8-13-24

USACE Public Meeting Presentation of H&H Results, August 13th, 6:30 PM at the Log Cabin. 

The US Army Corps of Engineers provided the results of their H&H modeling. Hydrology and Hydraulics Modeling can predict how the river (water level and velocity) will be impacted by E.Elm and Bridge St. dam removal. 

Here are the Public Meeting Slides.

Here is the Public Meeting Recording.

7-29-24

ACOE Section 206 Study Bi-Weekly Project Update

Present: Janet Cote, Project Manager (remote), Karin Orenstein (remote), William Mehr, Project Delivery Team-Real Estate (remote)


Bill Mehr (PDT-Real Estate) reviewed a real estate assessment questionnaire with Karin Orenstein concerning the Town’s capacity for acquiring easements needed to access and use property to implement the Tentatively Selected Plan (TSP).  Bill reviewed the estimated schedule for real estate work, which is tied to further work on project design.  Under this estimated schedule, PDT-Engineering would have from August 2025 to February 2026 to complete the design for the project.  At that point, PDT-Real Estate would prepare rights of way and maps for the project.  The Town would then have nine months, from February 2026 to November 2026, to acquire the eight easements currently identified.  Five of the easements would be for Town-owned property, one for the Yarmouth Historical Society, and two for property that is held privately.  If it takes the Town less time to acquire the easements, the subsequent work schedule could be moved up.  

Karin asked Bill whether easements could be donated.  Bill said that there is a process for donating easements.  It involves the property owner signing a “waiver of appraisal” letter, indicating that they are aware that they have a right to fair market value for what is essentially renting part of their property for three years, but they waive the appraisal and payment. Whether a property owner donates the easement or not, the Town needs to have a survey and title search done for each property/easement area.

Karin asked whether donated easements could count as work-in-kind by the Town (i.e., count toward the Town’s portion of the project cost).  Bill will check with counsel.

Bill will send the assessment questionnaire with the answers we filled in during the biweekly meeting to Scott LaFlamme, along with a sample submitted by another nonfederal sponsor.  USACE asked that Scott finalize the Town’s answers, sign the document and send it back to Bill.  (Bill subsequently sent these documents by email.)

Karin asked how the real estate work would be impacted if the Town opted to request a Locally Preferred Plan (LPP).  Bill clarified that this work schedule is solely based on the TSP being selected.  If the Town requests an LPP, PDT-engineering would have to develop the design, costs and benefits for the LPP, PDT-real estate would draw up new maps and rights of way, and the Town would likely have to get an appraisal and easement on an additional property.

Karin thanked Janet for her review and comments on the Town’s Frequently Asked Questions (FAQ).  The FAQ is live on the Town’s website.

Karin shared a number of questions and concerns shared by constituents in the past week.

The meeting ended abruptly at 4:33 when Karin’s power and internet cut out!  (Fortunately, both have since been restored in Yarmouth.)

END

USACE UPDATES

07-09-2024

USACE Section 206 Study Bi-Weekly Project Update

Present: Janet Cote, USACE Project Manager (remote), Bill Mehr, USACE Realty Specialist, TJ Atwell, USACE Public Affairs, Karin Orenstein (remote), Scott LaFlamme (remote)



END

07-01-24

USACE Section 206 Study Bi-Weekly Project Update

Present: Janet Cote, USACE Project Manager (remote); Thomas Mihlbachler, USACE Civil Engineer (remote); Karin Orenstein (remote); Michelle Cromarty (remote); Scott LaFlamme (remote)

END

06-25-24

USACE Section 206 Study Bi-Weekly Project Update

Date: June 25, 2024, 9:00am

Present: Janet Cote, USACE Project Manager (remote), Karin Orenstein (remote)

[Note to stakeholders:  Design & Implementation of the TSP through the USACE is funded 65%-35% (USACE-Town), while the difference in cost between a TSP and a more expensive LPP is funded 100% by the Town.  The Town can seek funding from other federal agencies for the Town portion of the Design and Implementation cost so long as the use of the other federal agency’s funds is authorized by law for this type of project.]

The meeting concluded at 9:43 am.

END

06-05-24

USACE Section 206 Study Bi-Weekly Project Update

Date: June 5, 2024, 3:00pm

Present: Janet Cote, USACE Project Manager (remote), Donald Faughnan, USACE Environmental Resources Specialist (remote), Karin Orenstein (remote), Scott LaFlamme (remote)



The meeting was adjourned at 3:35pm.

END

05-20-24

USACE Section 206 Study Bi-Weekly Project Update


Date: May 20, 2024, 3:30pm

Present: Janet Cote, Project Manager (remote), Bill Mehr, USACE, Karin Orenstein (remote), Scott LaFlamme (remote)



The meeting was adjourned at 4:15pm.

END

05-06-24

USACE Section 206 Study Bi-Weekly Project Update

Date: May 6, 2024, 3:30pm

Present: Janet Cote, Project Manager (remote), Karin Orenstein (remote), Scott LaFlamme (remote)





In addition to this public event, the USACE will be meeting on-site with impacted abutters. A specific date for site visits has not been determined but will likely occur in late June/early July as well. 



The meeting was adjourned at 4:25pm.

END

04-25-2024

USACE Section 206 Study "Tentatively Selected Plan (TSP) was presented to the Town officials: see Presentation to the Town of Yarmouth.

04-10-2024

USACE Section 206 Study Bi-Weekly Project Update 

Date: April 10, 2024, 1:30pm

Present: Janet Cote, Project Manager (remote), Karin Orenstein (remote), Scott LaFlamme (remote)

The meeting was adjourned at 2:25pm.

END

03-26-2024

USACE Section 206 Study Bi-Weekly Project Update 


Date: March 26, 2024, 10:30am

Present: Janet Cote, Project Manager (remote), Karin Orenstein (remote), Scott LaFlamme (remote)



The meeting was adjourned at 11:15am

END

03-11-2024

USACE Section 206 Study Bi-Weekly Project Update 

Date: March 11, 2024, 3:30pm

Present: Janet Cote, Project Manager (remote), Karin Orenstein (remote), Scott LaFlamme (remote)


The meeting was adjourned at 4:15pm


END

02-27-2024

USACE Section 206 Study Bi-Weekly Project Update

Date: February 27, 2024, 2:00pm. Present: Janet Cote, Project Manager (remote), Karin Orenstein (remote), Scott LaFlamme (remote)


Members of the USACE project team are steadily making progress toward finalizing a draft Tentatively Selected Project (TSP) report. Given their current timeline, Janet, Karin, and Scott reviewed upcoming milestones:


Other project updates offered by Janet included:


The meeting was adjourned at 2:46pm


END

02-13-2024

USACE PUBLIC VIRTUAL MEETING FOR THE ROYAL RIVER SECTION 206 AQUATIC ECOSYSTEM

Meeting Highlights:


Final Report (Jan 2024): https://drive.google.com/file/d/1pXBIMNqndqtB9i6eltvc6eaofTj3Pv0R/view?usp=sharing


Meeting Recording (Feb 2024): https://www.nae.usace.army.mil/Portals/74/docs/Topics/RoyalRiver/Royal%20River_Yarmouth%20Maine%20Public%20Meeting_20240213.mp4


Meeting Slides (Feb 2024): https://www.nae.usace.army.mil/Portals/74/docs/Topics/RoyalRiver/USACE_Royal%20River%20Section%20206_Public%20Meeting_Slides_Feb2024.pdf


END

02-05-2024

US ARMY CORPS OF ENGINEERS 

PUBLIC NOTICE OF VIRTUAL MEETING FOR THE ROYAL RIVER SECTION 206 AQUATIC ECOSYSTEM RESTORATION STUDY YARMOUTH, MAINE 

Interested parties are hereby notified that the U.S. Army Corps of Engineers (USACE), New England District, will host a virtual public meeting to provide an update on the Royal River Section 206 Aquatic Ecosystem Restoration Study in Yarmouth, Maine. The virtual meeting will be held on Tuesday, February 13, 2024, at 6 p.m. EST. 

The meeting can be accessed via WebEx at https://usace1.webex.com/join/cenae-pa , or join by phone at 1-844-800-2712 (U.S. Toll Free) or 1-669-234-1177 (U.S. Toll) and use Access code: 199 945 8471. 

The information about the meeting and the feasibility study, and recordings of the meetings (when available) can be found by visiting: https://www.nae.usace.army.mil/missions/projects-topics/royal-river-aquaticecosystem-restoration-study/ 

Questions and comments on the project and meetings can be submitted by mail to the attention of Janet Cote, USACE, Planning Division, 696 Virginia Rd, Concord, MA 01742 or emailed to RoyalRiverYarmouthME@usace.army.mil.

END

Announcement pdf file: https://drive.google.com/file/d/1BnXXqYdiEc4fCN8zG-cmB3RD9vTWZJ0D/view?usp=sharing

01-29-2024

Meeting Notes: Update Meeting with Janet Cote, Project Manager for the ACOE Section 206  study of the Royal River, Monday, January 29, 2024, at 3:00 PM (With scheduling follow-ups).  Present (all remote): Janet Cote, Nat Tupper, Karin Orenstein, and Scott Laflamme. 


Janet Cote provided the following status updates: 

Work is proceeding with all aspects of the study pending a consultation with the US Fish and  Wildlife Service regarding recommendations on if/how any interventions to further improve fish passage through the Middle Falls area. Work is moving forward on pace regarding the cost engineering estimates for removals and/or fish ladder modifications, and whether any such changes would be better considered and designed as a mitigation (follow-up) action. Also, work is continuing to complete analysis and reports other aspects of the assessment of options.  

The Corps is considering gathering additional information on prior dredge maintenance projects undertaken by commercial interests in the Royal River (in recent decades).  

Discussion followed on the timing and format of the public presentation tentatively planned for mid-February. The intent was/is to have the Corps host a public informational session to  provide the public with information on the progress and purpose of the study and lay out the  reporting and decision process going forward. The Corps’ plan has been to hold this as an on line (remote) informational session, with an opportunity after the Corps’ presentation for the  public to submit questions via chat or text to which members of the Corps’ Project Delivery  Team might be able to respond. 

Based on the conversations and the requests of some stakeholder, that plan has now been modified as follows:  

Monday, Feb 12th: Ben Loyd and Byron Rupp will schedule an in-person consultation with the Royal River Marina and Boatyard operators to discuss the project, and the concerns they each have relative to dredging and navigability issues, and hear other concerns they may wish to share about the challenges to their work relative to the role of the Corps. They will share and explain the preliminary indications of the sediment data and will listen to the marina’s concerns.  

Tuesday, Feb 13th: The Corps will hold a virtual public meeting, where all of the stakeholders and public will be invited to attend (log in). The entire PDT will be asked to be available on-line. The Corps plans on scheduling the evening meeting for 2 hours and will review what the Corps’ role is and what the elements and goals of the 206 Study are, and where we stand now relative to the project timeline. We anticipate there will be the ability to send in questions using the chat feature that Team members may be able to answer or consider. The current plan is that the Corps preliminary findings and recommended Tentatively Selected  Project will be recommended and reported around April 2024, with another public forum in an in-person format at a Yarmouth/local venue.  

The Town Council would thereafter consider the preliminary findings and Tentatively Selected Project and could either agree or petition the Corps to select a different “Locally Preferred”  from the available options. Thereafter, the Corps would proceed with the Tentatively Selected Project and the Locally Preferred Project (if different) through the remainder of the project.

Nathaniel J. Tupper/Town Manager 

January 30, 2024  These notes may be shared.  


Additional Explanatory Notes/Excerpts of the Project Schedule MP follows for reference only. NOTE: The 206-study process can be a bit difficult to follow sometimes, and we are moving toward a milestone point in the coming few weeks and months, so I’m pasting below some excerpts from the Project Management Plan that was circulated last year. I hope you find it helpful to remember or understand where we are in the process of the investigation.  

The next public briefing, tentatively scheduled for Mid-February 2024 (in whatever format/ venue is determined) will be a progress report and sharing of the work to date, as well as to explain the next critical steps.  

In April 2024 (or thereabout) the Corps is scheduled to issue a preliminary Detailed Project  Report and Environmental Assessment (DPR/ EA). That will be presented to the Town Council  and to the general public (date, format, etc. tbd). Current expectations are that the presentation will be an in-person presentation in a local public forum. The DPR/EA will include the Corps’  “Tentatively Selected Project” (e.g. dam removals(s), fish ladder replacements(s), do nothing, or some combination). The Town Council will need to deliberate and decide whether to have the Corps proceed with its Tentatively Selected Project (PSP) or to petition the Corps to consider a different “Locally Preferred Option”. The Corps will proceed to complete the Feasibility Phase of the Study on the Tentatively Selected Project (or the Locally Preferred Project if the request is approved). That completion of work is expected to take until about May of 2025 to complete.  

NJT: 1-30-24

Project Management Plan (PMP) Excerpt: Required Project Study Output: 

The required outputs of the feasibility study are an approved Integrated Detailed Project Report and Environmental Assessment (DPR/EA), including signed Finding of No Significant Impact (FONSI). The report will document the assessment of a narrow range of feasible alternatives and selection of a recommended proposal that meets the Section 206 authority criteria, is feasible, cost-effective, and is within funding constraints, and where real estate interests can be readily obtained by the sponsor. Cost-effectiveness is measured by a quantified output of environmental  benefits that an alternative may generate compared to the project cost to design and construct that alternative. The DPR/EA will document compliance with environmental requirements and will include coordination with Federal and state agencies. Feasibility analysis in the report will include assessment of real estate acquisition and access, feasibility-level cost estimate of a small range of alternatives (assume two plus the no-action), quantified ecosystem restoration benefits, environmental impacts, and ability to be permitted. The DPR/EA will refer to (without replicating effort) previous studies along with their associated documents. 

The PDT (Project Design Team) will undergo planning steps including problem identification and project purpose, inventory and forecasting conditions, alternative formulation and evaluation, benefit and cost analyses, and alternative comparison. Then the PDT will select a proposed alternative that meets the project purpose and is cost effective in providing ecosystem restoration benefits. This proposed alternative, known as the tentatively selected plan (TSP), will then be reviewed in a joint USACE New England District and North Atlantic Division (NAD) meeting for NAD approval to proceed to completion of the draft DPR/EA for technical review and public review.  

Once the draft DPR/EA is completed, the report will undergo a District Quality Control (DQC)  review at the USACE New England District, and the PDT will edit the draft report based on the  review. All functional elements from which staff is assigned to the project are responsible to assign staff for the DQC review and will certify that the work is accomplished consistent with the District’s Quality Control Plan (QCP). Then the DPR/EA will undergo an Agency Technical Review (ATR), USACE NAD review, and public review through public release of the draft report.  

An ATR is undertaken to "ensure the quality and credibility of the government's scientific  information" in accordance with this policy and regulations. This level of review will also cover any necessary National Environmental Policy Act (NEPA) documents and other environmental  compliance products. An ATR is mandatory for all decision and implementation documents.  

The PDT will address the various review comments and revise and complete the final DPR/EA  along with a FONSI. The USACE New England District will then submit this package to the  USACE NAD, followed by signature by the New England District Engineer, for approval to proceed to the next project phase – design and construction (DI) phase. 

The success of the project is highly dependent on the PDTs communication and cooperation.  Each member of the PDT (both team members and sponsor representatives) provides information and support that is essential for the project. Each project has a unique set of goals, challenges, and constraints that determine the importance of each team member’s role. General descriptions of team member responsibilities are also available in the CAP Programmatic PMP.

.

END

01-17-2024

Meeting Notes:  Update Meeting with Janet Cote, Project Manager for the ACOE Section 206 study of the Royal River.  Wednesday, January 17, 2024, at 11:00AM. Present (all remote): Janet Cote (USACE Project Manager), Nat Tupper (Town Manager), Karin Orenstein (Town Councillor), and Scott LaFlamme (Yarmouth Assistant Town Manager).

Janet Cote provided the following status updates:

Ben Loyd is finishing his report on sediment testing results and will release that after an internal quality review.  He has indicated that the results overall are “clean” with no finding of mercury from the area previously discovered by Stantec (or elsewhere), and the PAH’s detected by Stantec (below threshold levels of concern concentrations) are still detectable but at even lower concentrations and would not be a permitting barrier for dam removal or dredge projects.

Tom M. (Mihlbachler) was able to incorporate Stantec’s recent probing data into the H/H model.  The data  supports the observation that the river is regularly scoured out to bedrock and little sediment is being held or settled behind the dams, except at riverbanks (the edges).  

Dr. Haring (ERDC) met with the Corps to discuss his findings from the site visit that was completed in November 2023. He is currently writing a report to describe his findings regarding sediment transportation in the Royal River. His observation was to the effect that conditions upstream of the Elm Street Dam (shallow soil layer or lack of soil, with exposed bedrock) are conducive to safe dam removal relative to downstream sediment impacts.  

Dr. Haring did anticipate a recreational impact: Because the H/H model anticipates the normal low water levels upstream of the Elm St dam will drop by about 4 ft with dam removal, river flow conditions will change recreational choices (with more shallow fast flowing areas and less deep flat-water area. This would support canoe and kayak recreation but not larger boats/rafts.   

Dr. Haring will plan to revisit the site in better weather conditions to do additional assessment of tributary conditions and contributions, to project what impacts, if any, will be  relative to mitigation measures that might be planned such as plantings and tributary bank stabilization.  Dr. Haring anticipates it would likely take 5-10 years for the revised equilibrium condition of the riverbanks and tributaries to re-establish. Final design and implementation of tributary impacts mitigation measures, if needed,  would be in the final Design and Implementation Phase (if action after the Feasibility Study/Permit Phase is advanced). 

The Construction/Civil Engineering team are putting together preliminary design and cost options for 4 alternatives that include the replacement of the fish ladders (with retention of the dam) and removal of both the dam and fish ladder at both the East Em Street and Bridge Street sites. The no action alternatives will also be evaluated in the cost-benefit analysis. 

Donnie F. will be assessing the environmental and habitat restoration impacts and benefits of each alternative.  Habitat benefits are broadly viewed, but there is a particular interest in fish passage outcomes.  {Note: Costs and Benefits consider a wider set of considerations including but not limited to water quality, temperature, aeration, recreational/cultural/historic impacts, O/M costs, flood, infrastructure, scour, safety etc.}

During the on-site Coordinated Site Visit with the resource agencies, which occurred in November 2023, the USFWS and National Marine Fisheries Service expressed concerns about fish passage at Middle Falls. The USFWS has been asked to consult with the Corps on developing options that would increase fish passage through Middle Falls. A separate (add-on) cost will be estimated for any modifications or actions recommended by the USFWS relative to Middle Falls and the back channel around Factory Island to encourage/assist some fish species movement.

Janet will follow-up with the Town on the quarterly project financial status and non-federal share requirements anticipated through September 30, 2024 (the end of the Federal Fiscal Year)  

The group discussed a public presentation of findings and progress to date to be made by the Corps in mid-February and tentative dates were proposed.  Janet will check with the Public Affairs Office on the dates and format, but we anticipate a remote access presentation with opportunities for the public members to be recognized to ask questions and/or to submit questions online during the meeting.  Janet will circle back once she can confirm the availability of date(s) and presenters so the Town can give notice to the public.  


END

12-18-2023

Meeting Notes:  Update Meeting with Janet Cote, Project Manager for the ACOE Section 206 study of the Royal River.  Present (all remote): Janet Cote, Nat Tupper, Karin Orenstein, and Scott Laflamme.

Work is proceeding but the Corps is waiting for data in four areas of investigation:


While waiting, engineering is working on design plans (and cost estimates) for full and partial dam removals.  And cost/benefit assessments are being outlined relative to overall aquatic restoration goals, safety and O&M costs for the current structures.  

END

12-04-2023

Meeting Notes:  Update Meeting with Janet Cote, Project Manager for the ACOE Section 206 study of the Royal River.  Monday December 4, 2023, at 3:00 PM Present (all remote): Janet Cote, Nat Tupper, Karin Orenstein

The Coordinated Site Visit was led by Donnie F.  Tuesday, Nov. 7 for State and Federal review agencies went well.  In addition, officials from the ERDC [Engineer Research and Development Center for the USACE] visited the area river and tributaries to look at the issues of sediment transport.  Further review of Middle Falls fish passage challenges, if any, remains a part of the assessments and any future cost-benefit analysis of options.  

Lab results for analysis of sediment samples taken by Ben Loyd are still not back yet.  Janet was not able to get an estimated delivery date update.  As reported before, once the lab results are back Ben will review and assess any findings and implications and we will schedule a virtual public presentation.  It is evident that it will not be prior to Christmas.  

Since the last report, Nat has contracted with Stantec to gather additional sediment profiling as requested to provide raw data to the Corps to input to the H/H model.  The Corps confirmed that this expense will be eligible as a Work-in-Kind expense and therefore a credit against the Town’s cost share.  Work will be done as soon as river conditions permit it to be done safely. 

Janet was reminded to inquire about the prior sampling results period of validity in review and permitting standards.   And Nat drew the Corps’ attention to questions of current dam structural stability with respect to apparent movement of stone blocks at the Elm Street dam. A request was made to bring the information presented in the New Meadows proposal to the attention of the design/engineering teams who are working on designs for full or partial removal of the dams as possible options. 

END

11-27-23

Meeting Notes: Update Meeting with Janet Cote, Project Manager for the ACOE Section 206 study of the Royal River.  Present (all remote): Janet Cote, Karin Orenstein

Janet Cote has returned from a brief leave and sought updates from team members.  Some team members have not yet provided updates as they have been out of the office for the Thanksgiving holiday since Janet’s return.

Ben Loyd advised that the lab processing the sediment samples is delayed well beyond the 30-day estimate for turning around results. The lab now expects results in “early December.”  As Ben will need time to review and analyze the lab results before a public meeting, and we will start getting into December holidays, it is not likely that we will be able to hold a public meeting about the sediment testing until January.  The ACOE Public Affairs Office (PAO) advised Janet that Tuesday evenings tend to work well for public meetings, so we “lightly penciled in” Tuesday, January 9th in the early evening for the public meeting.  As Ben’s ability to report on the results depends on receiving them, we will wait to officially select a meeting date until he receives the lab results.  The meeting will be virtual and moderated by PAO staff.  The PAO will also advertise the meeting in advance. 

The engineering team has been working on alternative designs for river restoration projects at each dam.  For each dam, they are creating designs for (1) full dam removal and (2) partial dam removal.  A third option, (3) fish ladder restoration, is being investigated by Donnie (ecologist) with input from FWS. So, for each dam, there are three options being designed plus the no-action option, which does not require a design.  All of these will be subjected to a cost-benefit analysis. For non-math folks, that’s 16 permutations – four options for dam #1 x four options for dam #2.  Full dam removal means removing all rocks or concrete down to the shoreline.  Partial dam removal means removing rock in the water, but leaving some elements of the original dam.  For example, partial dam removal at the Elm Street Dam could involve removal of the rocks on the right-descending bank, but leaving rocks in place on the left-descending bank where there is less flow.  

The cost-benefit analysis will also need to take into account factors that don’t easily lend themselves to having assigned dollar values.  For example, partial removal of the Bridge Street dam could have a similar cost-benefit analysis as full removal, but full removal may be preferable because there may be safety concerns if we leave partial structures in place.  It’s Janet’s task to see how factors like safety are included in the analysis.

Other teams are waiting on work currently being completed.  For example, the team handling the cost-benefit analyses will rely on the engineering team designs, Donnie’s model of costs and benefits, the sediment sample lab results, etc.

ERDC completed its field work and Tom M. (water modeling) is in contact with them.  ERDC is studying sediment transport and re-deposition at no extra cost to the Town.

ACOE reviewed two proposals the Town received for sediment transect probing to determine the amount of sediment at various cross-sections of the river.  Karin noted that Nat is in the process of hiring Stantec and that there may be some delays in performing the work because of recent and upcoming rainstorms that raise the water level.  The Town’s payment for this analysis is considered “work in kind” that is credited to the Town under our contract with ACOE.  Estimating the amount of sediment is relevant to the cost-benefit analysis, as is the sediment testing being done in the lab.  If the sediment lab results show the sediment is clean, it will be easier and less expensive to remove and dispose the sediment upland.  The amount of sediment necessarily impacts these costs as well.  

END

11-06-23 

Meeting Notes:  Update Meeting with Janet Cote, Project Manager for the ACOE Section 206 study of the Royal River, along with Byron Rupp, ACOE.  Present (all remote): Janet Cote, Byron Rupp, Nat Tupper, Karin Orenstein

The Coordinated Site Visit will be led by Donnie F.  Tuesday, Nov. 7 for any State and Federal review agencies.  It is still planned (subject to confirmation) that Tom M. will meet with ERDC on site to look at the river and tributaries to assess sediment transport and redeposition issues.   

Lab results for analysis of sediment samples taken by Ben Loyd are not back yet.   Once they are back Ben will review and assess any findings and implications and we will schedule a virtual public presentation.  At the presentation, the Corps will provide a summary of the sampling locations and how/why they were selected along with a summary of the findings.  The Feasibility Study, which will be issued later, will provide full details and supplemental data tables as well as an explanation of the findings. 

Janet will inquire about the time period of testing results (how long are current and prior samples and findings considered valid?) for the purposes of permitting in the event that sediments and/or dam removal are recommended.  

The request for addition sediment profiling by the Town was more extensive than anticipated, so Nat had reached out to Stantec and to New Meadows Environmental LLC  to seek a proposal to perform the additional profiling work as requested to provide raw data to the Corps to input to the H/H model.  It is anticipated that this will be Work-in-Kind eligible expense (i.e., credit the Town’s cost share).  Nat is waiting for a proposal (s)).  

Janet provided future cash flow estimates as requested.  

Regarding scheduling the public presentation about the sampling, all agreed that Ben Loyd needs whatever time is necessary to complete his review and make findings, after which a public presentation would be welcome.  If the schedule pushes up against Thanksgiving week, we would delay the presentation until early December, date tbd.  

10-26-23

Meeting Notes from Nat Tupper:  Present (all remote): Janet Cote (USACE Project Manager), Nat Tupper (Yarmouth Town Manager), Karin Orenstein (Yarmouth Town Councilor)

The Coordinated Site Visit will be led by Donnie F the second week in November for any State and Federal review agencies.  Donnie is particularly interested in the insights of NMFS and USF&W Service advisors.  

Also that week, the ERDC (the Corps’ research group) will visit the site. ERDC is called in (without charge to the project funds) to assess and advise particularly on issues of sediment transport and redeposition. 

As expected, lab results for analysis of sediment samples taken by Ben Loyd are not back yet.  Once they are back Ben will review and assess any issues of concern.  Janet indicated that Ben plans to provide the Town with a sampling location map as requested as soon as he is back from other field work (different project).  That map should be sent shortly. (Note: Subsequently received and attached here.)

Tom M’s H/H model is complete for the baseline (current) conditions, subject to QA/QC review.  However, the model is intended to be able to run and guide the Corps in a variety of change scenarios (e.g., removal of one or both dams, new or rebuilt fish ladder(s), partial removal(s) etc.)  So, he will wait for the design option scenarios to plug into the model.  Those designs will be developed with advice of the coordinating agencies such as USF&W, NMFS, and others.  The Site visits will help move those design concepts forward.  

The Corps had previously requested that the Town assist with additional investigation of bottom conditions above the Elm St dam to locate the nature and scope of conditions so that gravel, cobble, ledge, fine silts etc. can be quantified and located.  The Town noted that weather and flow conditions are favorable now and so it would be best to get instructions soon so that the work can be safely done.  

Janet will meet with the Project Design Team tomorrow and will try to get their forecasts of work schedule and products to help predict cash flow requirements.  

See sediment sampling site maps below:

END 

(see two map attachments below)

Royal River Bridge St. Sediment Sampling Site Map USACE 206. Fall 2023. This map was released to the public by the U.S. Army Corps of Engineers © U.S. Army Corps of Engineers. 

Royal River Elm St. Sediment Sampling Site Map USACE 206 Fall 2023 This map was released to the public by the U.S. Army Corps of Engineers © U.S. Army Corps of Engineers. 

10-12-23 

From Nat Tupper’s (Yarmouth Town Manager) Notes on Meeting with USACE. Present: Jane Cote (USACE Project Manager), Nat Tupper, Karin Orenstein (Yarmouth Town Council) 

Ben Loyd (USACE) collected Royal River sediment samples the week of October 2 and those have been sent to the lab for analysis—about 30 days for test results. The Town requested a map of actual sampling locations be sent as well. 

The town requested a video session (with public engagement) for the Corps to share findings on this aspect of the work in progress in the week of November 27- Dec 1 if findings are ready and the schedule permits; or early December if more time is needed. 

A meeting between the 206 Project Delivery Team (PDT) and the ERDC [U.S. Army Engineer Research and Development Center] had been held this week and plans were being formulated and schedules coordinated for the ERDC to do its site visit in early November. The ERDC will look further at issues and data related to physical sediment and river conditions as well as adjoining tributaries. 

The Corps is preparing a request for the Town to do additional probing of material/river conditions just upstream of the Elm Street dam to confirm or correct assumptions and understandings of the amounts and locations of fine-grained sediment as well as large cobble, gravel, or ledge bottom. This will help with cost estimating for removal and upland disposal of sediment before any work is done. 

Janet will check back with Tom M [Tom Mihlbachler, USACE H&H Engineer] for a status update regarding the completion of the H&H modeling, subject to QA/QC review and verification. 

Nat reported on findings related to ownership of the penstock with the mill owner and adjoining property owner. 

The Town has contracted for engineering work to understand what action may be required regarding the granite block retaining wall at Grist Mill Park. It is understood that work on the dam(s) or fish ladder(s) upstream would have no impact on the wall and is not part of the 206 or Army Corps work. But the Town needed to have a structural assessment completed for public safety. 

The group revisited and reaffirmed a prior understanding that in addition to dam removal (or not) options, that partial removal or modification of either or both dams and/or fish ladders could be considered if such option are effective at achieving habitat/aquatic restoration results, but all options are subject to determinations on a host of other important considerations including, but not limited to engineering/structural concerns, costs, aesthetics, historic references/preservation, public safety, impacts on and preferences of abutters, wetland and aquifer impacts, flooding and scouring concerns, recreational values, etc. The feasibility study is intended to identify and evaluate best options. 

The Coordinated Site Visit of review agencies is still to be rescheduled- probably in November when more agencies can attend, and, in particular the NMFS [National Marine Fisheries] and the USFW [US Fish and Wildlife] staff. 

We confirmed through Janet that the Aquatic Restoration (206) Study is maintaining close contact with the navigation division so that whatever action may be taken (if any) for restoration may be anticipated and coordinated with navigational maintenance.

Janet had sent a quarterly financial statement (federal and local funds drawdown statement) on the feasibility study to date and will provide us a future cash flow estimate soon. 

END

9-27-23 

From Nat Tupper’s Notes on Meeting with USACE. Present: Jane Cote, Nat Tupper, Karin Orenstein (Yarmouth Town Council), Heather Abbott (Yarmouth Town Council) 

Janet Cote reported that Ben Loyd will visit next week to get sediment samples to test for pollutants in the Royal River. An updated sediment testing plan/map will be provided to the town. Janet’s expectation is that getting sample test results back from the labs generally requires about 30 days and thereafter Ben will need some time to review and consider those lab findings. 

The ERDC (USACE Engineer Research Development Center) will be providing an assessment of sediment mobilization issues. No date was provided for when the assessment will be done. 

Donnie Faughnan will lead a Coordinated Site Visit team (representatives of review and advisory agencies) to familiarize them with the sites. 

The Corps’ Public Affairs Office staff will take the lead on scheduling, planning and moderating a public informational session which will be in the evening and by remote access. But not during Thanksgiving week. 

END


9-11-23 

From Nat Tupper’s Notes on Meeting with USACE. Present: Janet Cote, Nat Tupper, Karin Orenstein (Yarmouth Town Council), Heather Abbott (Yarmouth Town Council): 

Members of the Project Delivery Team (PDT) visited Yarmouth on the morning of Sept. 6 and walked to view the East Elm Street dam, fishway, History Center, and St Lawrence and Atlantic trestle, Middle Falls, Beth Condon pedestrian bridge, Route 1 bridge, Bridge Street dam and fishway. The team drove to Grist Mill Park to view the falls and crossings, and then to the Harbor, MCRR trestle at Sligo Road, and finally Baston Park in North Yarmouth (at Route 9). USACE Team:Janet Cote – Project Manager/Planning, Parker Murray – Economics, Donnie Faughnan – Environmental, Grace Moses – Environmental, Tom Mihlbachler – H&H Engineering, Matt Fleming – Geotechnical Engineering, Marc Paiva – Cultural Resources, Kevin Hebard – Civil Engineering, and Mike Andryuk – Structural Engineering TOWN: Nat Tupper, Karin Orenstein, Clark Baston (North Yarmouth DPW) 

A Coordinated Site Visit of the team is being scheduled for late October or early Nov. A public informational session is penciled in for early November if Ben Loyd has sediment sampling results analyzed by then. 

Janet will provide some cash flow/drawdown projections for future planning. Nat will inquire if any additional benthic survey data for the upper reaches of the impoundment has been done (in addition to the Stantec findings). 

END


8-28-23 

From Nat Tupper’s Notes on Meeting with USACE. Janet Cote (Project Manager for the USACE) and Nat Tupper (Town Manager) meeting: 

A virtual Agency Coordination Site Visit will be held Wed., August 29. Several State/Federal agencies are anticipated to check in, including USFWS, NMFS, USEPA, MEDOT, ME Dept. Inland Fisheries and Wildlife, Historic Preservation Offices (3), Native American Tribes/Nations (5). 

Janet confirmed that sediment sampling will be discrete (not aggregated) samples, and to the extent that there is layering of sediment in the samples (cores), separate analysis will be done for the various layers. Janet reported the Corps’ determination that additional sampling in the impoundments is not necessary based on the amount of testing and analysis conducted [are reported] in prior studies, and because of the high degree of transport of suspended fines over the dam (Bridge St). Except for areas immediately upstream of the Elm Street dam, additional testing above Elm Street is not needed. Sediment transported downstream to areas immediately upstream of the dam will indicate contamination, if any. She will send a map of proposed sampling locations. 

Janet will check back with Tom M (H/H Modeler) to give us a status update on completion of the draft model. Janet thought he may be only needing QA/QC review now, but she was not sure and will reach out to him. She was reminded that we are interested in five study findings related to the H/H model including: Scour, Flooding, Recreational Impacts, Archaeologic and Historic Resources, and Sediment Transport/Removal. 

Post Meeting Addendum Note from Janet Cote: “I spoke with Tom about your questions on the H&H modeling. The model will be finalized when we develop the Tentatively Selected Plan (winter 2024). With regard to the considerations below, the H&H model will help to inform Tom and other members of the team on the impacts of the alternative on these topics. And they will be addressed in the feasibility report. For example, #4 archeological/historical sites. The H&H model will provide a predicted level of draw down on the river at different flow levels for each alternative that we are considering. Marc will take that information, and with the data provided from the Maine SHPO, will describe the impacts of each alternative on those resources.” 

A stakeholder’s note of inquiry was forwarded to the Corps on August 18 includes a comment about ledge or other barriers to fish passage (other than the dams). That inquiry was acknowledged; the question is not new, and the Corps is aware of prior identification and projects associated with ledges and barriers (granite blocks). But the question was referred back to Donald Faughnan and the Project Team for consideration. 

We confirmed our intention to wait for sediment sampling test results and analysis to schedule a public virtual meeting to share the still early findings and work to date. 

Nat asked about removal of the penstock pipe which blocks access to the block retaining wall at 80 Bridge Street. We would like to determine if removal of the penstock can be incorporated into the project construction when/if any construction occurs which involves dam removal or alteration. Janet will review with the structural engineering and real estate team members. It is possible that it may have to be a 100% local sponsor project element, depending on whether or not its removal is deemed essential to the project scope.

END

8-14-23  

From Nat Tupper’s Notes on Meeting with USACE. Town of Yarmouth meets with Janet Cote (New USACE project manager) who conveys the following: 

USACE will set up a virtual meeting with federal and state agencies. 

2. A project management plan will be circulated to the project management team and town. 

Ben Loyd is scheduled to do sediment sampling in early September and Janet Cote (project manager) will confer with him to estimate a time schedule when testing results are returned and considered by the team. 

Results and analysis will take about 30 days after the samples are submitted, so Ben suggests a November public meeting if sharing that data is an objective. 

The sediment work will include grain size analysis of discreet samples i.e., sieve testing (not composite samples). Nat Tupper (Town Manager) reported that Maine DOT announced replacement of the Rte. 88 bridge over Royal River is now on their work schedule (2025/2026 constructions seasons) and suggested a contact with the engineering/planning teams of the ACOE and MDOT should be established so any design or potential construction activity is informed. 

END

4-4-23 

From Nat Tupper’s Notes on Meeting with USACE. New USACE project manager Janet Cote has been hired for the Royal River Restoration project (FID 206) Mr. Rupp’s (USACE interim project manager) understanding was that the sediment sampling and analysis was not part of Phase 1 but would be a part of a subsequent phase. However, since there is no Project Management Plan in place yet, the question is largely academic as there is no disagreement as to the need for the work to be done. The essential difference is whether or not the Town’s initial payment was intended to cover the local cost share or not. Mr. Rupp could not determine from the files how Kristine Reed (original Project Manager) had arrived at her cost estimates and in which phase of the study the various tasks were to be accomplished. The Cost-Sharing Agreement between the Town and the Corps does establish the total estimated project cost and local vs federal shares. We agreed that a detailed Project Management Plan (PMP) would have been helpful to clarify the steps, sequences, tasks, schedules and projected costs, and is the customary way that the Corps approaches these studies. END

3-17-23

RRA Summary of USACE Zoom PROGRESS REPORT to the Town of Yarmouth. March 17, 2023 (click VIDEO Link for the full meeting) Presented by: Tom Mihlbachler, Army Corps H/H Modeler, Water Resources Engineer and Byron Rupp (Interim Project Manager) 


PROJECT OVERVIEW (Byron Rupp, USACE Interim Project Manager, provided slides stating the following) 

1. Purpose of the project is to assess the removal of the two dams above head of tide on the Royal River owned by the Town of Yarmouth: Bridge St. dam and Elm St. dam, both dams have nonfunctioning fishways. 

2. Proposed feasibility study will develop an array of alternatives to support the fish passage restoration goals. 3. Alternatives could include: a. no action alternative make no improvements to the project area (fish barriers remain); b. dam/fishway removal, partial removal or modification of existing structures; c. new fish passage structures. 


RESULTS OF H&H MODELING (Tom Mihlbachler, USACE Engineer, said that these are draft modeling results, which have not been through a QC process and have not been finalized by USACE.) 

A. WATER VELOCITY: H&H Modeling shows water velocity and flow with and without dams. 

1. At the First Falls (Grist Mill) with and without the dams the [flow] images are almost identical and so we would not expect to see a scour concern during a 100 year storm. 

2. At the Bridge St. dam during a 100-year storm event without the dams, there is a significant increase in water velocity through the bridge site itself due to the narrowing and lowering of the floodplain through that area. The floodplain footprint within the impoundment with the dam in place is greater than without the dam. 

3. At the Elm Street dam during a 100-year event without the dams, there is an increase in flow around the dam itself and there is flow through the Foundry Channel. During “normal” events, flow through the Foundry Channel might not occur. 

B. RIVER ELEVATION: H&H Modeling shows river elevation with and without the dams 

1. River elevation change at low flow 35 CFS (e.g. September) without the Bridge St. dam is a decrease of 3 feet in its impoundment and without the Elm St. dam is a decrease of 4-5 ft in the Elm Street dam impoundment. 

2. River elevation change at 300 CFS (e.g. March): would be similar to without the dams. 

3. River elevation change during a 100-YR event (10,536 CFS) would be basically the same with and without the dam. (A 100-YR event = 1% chance of happening). 


USACE COMMENTS: (Byron Rupp, USACE Interim Project Manager) Bathymetry around the Elm St. dam is not complete. Additional probing behind the Elm St. dam is needed to find the sediment volume—dredging before the construction is possible. Rupp states there’s a lot of good literature on the sediment that we can use to inform the study. Bryon Rupp stated, “This spring USACE will work on site to collect the sediment data when it is safe to do so.” 


USACE PROPOSED NEXT STEPS (Byron Rupp, USACE Interim Project Manager)

1. Affirm the Town wants to move forward with the study 

2. Assemble project delivery team 

3. Develop project management plan 

4. Develop sediment analysis plan 

5. Establish regular check-ins with community.


END

2/17/23 

Nat Tupper (Yarmouth Town Manager) advises interested parties that the USACE H/H model presentation will take place via Zoom on March 17, 2023 at 10:00AM.

02/09/2023

TM Nat Tupper advises interested parties that there will be a presentation of the USACE’s draft H/H model in March 2023.

12/16/2022

Byron Rupp (interim project manager) advises TM Nat Tupper (Town Manager) that data for the H/H model has been collected, they are moving forward with modeling, and he will have an update in mid-January.

11/15/2022

In an email to RRA co-chair Christine Force, TM Nat Tupper reminds RRA that completing the H/H model doesn’t mark the end of the H/H study. USACE will still need to run the model “with various scenarios to understand impacts on a variety of potential concerns (scour, sediment transport, structural and historical considerations, habitat and fish passage, etc.)….”

~11/2022

USACE conducts bathymetry behind the Elm Street dam. The same team evaluates the harbor for dredging.

~10/2022

At the Maine Dredge meeting, as recorded in the meeting minutes, Dr. Christine Reed (project manager) says that the Yarmouth first phase of the 206 study was 85% complete.

~10/2022

During the fall Dr. Reed leaves, and Byron Rupp becomes interim project manager.

~9/2022

RRA learns from TM Nat Tupper that Dr. Reed (project manager) says the model will be done in a couple of weeks.

7/18/2022

Senator King's office (John Brady) responds to RRA that USACE stated that the work would be done in September and advises the RRA to wait.

7/12/2022

Disappointed by the lack of progress, the RRA sends a letter to Senator King's office.

~6/2022

During a telephone call with Nat Tupper (Town Manager) to discuss modeling progress, Dr. Reed (USACE project manager) says it will be done by August/September.

~6/2022

Dr. Reed (USACE project manager) does NOT update Town Manager Nat Tupper in May.

~5/2022

Nat Tupper (Town Manager) reports that USACE is reviewing the Stantec reports on its sediment study (as a replacement or preparatory work for USACE’s own, yet to be commenced sediment study?).

04/01/2022

During a telephone call with Nat Tupper (Town Manager), Dr. Reed (USACE project manager) advises that Tom Mihlbachler (USACE Engineer) is working on the H/H model and is dedicated to that project for the month of April. Dr. Reed will be away in April and will provide an update on the model and project status when she returns in May. Tom reported that so far all the data provided (e.g. the Stantec work) is aligning very tightly with the data and modeling work done by USACE which adds confirmation of the reliability of that work done. It appears that USACE did not take sediment samples before winter 2021-22.

11/2021

RRA is advised that USACE would aim to have their environmental sampling done before winter weather sets in.

10/2021

Dr. Reed (project manager) views the project as commencing in October (two months after contract is fully executed).

Although the Town of Yarmouth has requested a scope and schedule of work, neither is provided.

~8/2021

USACE signs the contract (two months after TC signs it).

~6/2021

Yarmouth Town Council signs the negotiated contract with USACE.

~2/2021

The USACE says the Town needs to contract for the full project.

Town attorney works with USACE to revise the contract wording to allow the Town to pull out of the program after Phase 1, per Dr. Christine Reed (project manager) representation. Resolution of this conflict results in a multi-month delay.

01/21/21

Portland Press Herald, 01-21-21. Yarmouth commits to studying removal of Royal River dams.

01/7/2021

TC unanimously votes to commit to USACE 206 Restoration Feasibility Study (Phase I) and approves funding.

During the public debate on the USACE 206 Restoration Feasibility Study (Phase I, Feasibility Study), various Town Councilors indicate support for removal of the Bridge Street dam, but agree to wait based on USACE’s representation that the Phase 1 studies – the results of which the Town would otherwise need to duplicate at its own expense – will be completed within a year. Marina representatives state they have no opposition to dam removal in principle but ask that their interests be taken into account and note that they trust the USACE to conduct proper testing.

01-07-21

Royal River Rod and Gun Club, 01-07-21. Letter to the Yarmouth Town Council in support of dam removal.


01-01-21

Royal River Alliance, 01-01-21. Letter to the Yarmouth Town Council Recommending to Enlist the USACE and Begin Bridge St. Dam Permitting. 


01-01-21

Maine Dam Removal Permitting Process, 01-01-21. Outline of permitting process for dam removal in Maine. 

12/10/2020

At a Town Council ops meeting, Dr. Christine Reed (project manager) made the following representations via zoom:

USACE is not fast or cheap, but they do cost sharing.

—A typical feasibility study is 18-36 months.

—It can take 3-5 years to complete a project with USACE.

—The Town could contract in phases with the USACE. Upon completing a contracted phase, the Town could choose not to proceed with remaining phases.

—The estimated full project cost is $660,000 (or $280,000 after $100,000 of federal funding and 50/50 cost-sharing of the remainder). This estimate is high because it covers all possibilities, including studies USACE would need to conduct if dam removal is not feasible. However, if initial hydrology/hydraulic (“H/H”) and sediment studies show that dam removal is feasible, any additional studies would become unnecessary and the total cost will be substantially reduced.

—This estimate does not include construction costs, which are shared 65/35.

—The first phase would consist of H/H and sediment studies and would be completed in approximately one year. The estimated cost for that is $180,000 or $52,500 with federal funding and cost-sharing. When that phase is completed, we will know if dam removal is feasible (which would obviate further studies and reduce the overall project cost).

—The USACE would not rely on the work of others (like Stantec) but instead will complete the project using its own methodology. This does not mean there was anything wrong with prior studies; USACE just does things its own way.

—The Town could contract with USACE to look at both dams and still decide to remove the lower dam while USACE is doing its work.

—The USACE “would never take a dam out and just [let] all the sediment behind it, just float down[stream]. It would kill everything, whether it was contaminated or not. We generally [de-]water the area, we dry it out and” remove the dry sediment “put it somewhere uplands, not in the water.”

12-03-20 

Royal River Alliance, 12-03-20c. Letter to the Yarmouth Town Council Regarding Reaffirming Recommendations.

11-10-20

USACE, 11-10-20. "Royal River Next Steps Q&A with USACE". Transcripts/Recordings  from a virtual meeting. 

10-25-20

Royal River Alliance, 10-25-20b. Letter to Yarmouth Town Council Regarding Recommendations on Bridge St. Dam Removal.

09-09-20

Royal River Alliance, 09-09-20a. Letter to the Yarmouth Town Council Regarding the USACE Federal Interest Determination Reports. 

08-06-20

Royal River Alliance, 08-06-20. Letter to the Yarmouth Town Council Regarding the Bridge Street Dam and penstock.

~4/2020

USACE notifies the Town of Yarmouth that they have completed the USACE 206 Evaluation and it meets their criteria to proceed. US Army Corps of Engineers, 2020a.  Federal Interest Determination: Royal River, Yarmouth, Maine 206 Aquatic Ecosystem Restoration.  At the request of the Town of Yarmouth.

04/03/2020

Federal Energy Regulatory Commission approved Sparhawk Mill surrender of exemption. On November 6, 2018, Sparhawk, LLC (Sparhawk), exemptee for the 270 kilowatt (kW) Old Sparhawk Mill Hydroelectric Project No. 8417, filed an application to surrender its exemption from licensing. The project is located on the Royal River in the Town of Yarmouth in Cumberland County, Maine. The project does not occupy federal

lands.

~06/06/2018

The Conservation Law Foundation filed a notice of intent to sue (on May 11) against the Town of Yarmouth, the Sparhawk Mill owner Allan Jagger and the real estate agent Michael Cardente for alleged violations of the federal Clean Water Act.

10/12/2017

The Department of Inland Fisheries and Wildlife Service noted, "In the summer of 2017, Service staff surveyed the bypass to assess potential for passage in this side channel. Due to its long, circuitous path around Factory Island, the side channel is characterized by predominantly mild slopes with occasional drops and short, steeper slopes over ledge outcroppings. Remnant mill foundation stone can be found throughout the area. In general, the side channel appears passable over most of its length though water depths were shallow at the time of this survey. Two locations that may hinder fish movement were identified. Moving upstream, the first potential impediment was a wide ledge bench of moderate slope. The bench

induced shallow, sheet flow over this flat bedrock section. The combination of fast water and shallow depth would clearly inhibit movement of American shad, and to a lesser degree, river. herring. The second potential impediment was a short cascade towards the upstream end of the side channel. Alosines prefer to move over hydraulic drops through submerged nappes and, generally, are not known to leap over free overfalls (in the way salmonids do). The degree to which both sections impede upstream movement is highly dependent on flow in the channel. Significant improvements to the passage conditions at these sites might be accomplished through alternations to the ledge outcroppings and/or movement of large rocks. This work might be accomplished in 3 to 5 days by a small crew with access to a generator, compressor, pneumatic hammer, and grip hoists. These enhancements would be relatively low cost and should be considered viable alternatives."

~09/17/2015

Yarmouth Town Council votes 6-1 not to take action or further consideration on removal of the Bridge St. dam.

04/08/2013

The Town of Yarmouth with assistance from Landis Hudson (Maine Rivers) submits a Letter of Intent to request USACE assistance with Royal River restoration. "The request called for studying the potential for restoring fish passage through the removal or alteration of two dams owned by the Town."—USACE

07/31/2012

Royal River Rolling Stones Project, 2012. Factory Island Back-Channel, Yarmouth, ME.  Portland Press Herald, 7-31-2012


02/19/2009

The Yarmouth Town Council appropriates funds "to study alternatives for improved fish passage and river restoration alternatives on the Royal River".